Before
  • 3 Bedrooms
  • 2 Bathrooms
  • House Floor Size 93 m2
After
  • 5 Bedrooms
  • 3.5 Bathrooms
  • House Floor Size 120 m2
Inital Discovery
Jeremy discovered Elite Additions through a Google search and was impressed by the positive reviews on the company’s website. The project had already received approval for planning, so Jeremy was ready to move forward with selecting a builder.
Consultation
Upon contacting Elite, the team provided a quote based on the approved plans. Jeremy was curious about how other clients typically select their prime cost items—such as colours, tiles, toilets, and vanities. In response, the team explained that most clients either choose these items themselves or opt to work with an interior designer. Elite recommended Kate, an interior designer from Reset Co., who could assist with design decisions throughout the project. After receiving a quote from Kate, Jeremy decided to proceed with her services, and Kate was able to liaise directly with him on design details and layout.
The Design Challenge: Joining a Detached Garage to the Main House
1. One of the standout features of Jeremy’s project was the plan to join a detached garage to the main house, which did not originally have internal access. This involved the addition of a clearstory window and a 5-level staircase, both of which presented significant design and engineering challenges. 2. The engineering plans provided by the original consultant were inadequate and did not meet the necessary structural standards. In response, Elite Additions took the initiative to redesign the structure themselves. Using SketchUp, the team created a 3D model of the proposed changes and presented it to Jeremy for approval. Once the design was finalised, Elite worked with a separate designer to create shop drawings, which were then submitted to the engineer for sign-off. After some adjustments, the new plans were approved, and the team was able to move forward with the build.
Overcoming Logistical Hurdles: Installing a Feature Staircase
The staircase and clearstory window were a key feature of the project and proved to be one of the most complex aspects of the build. With 7-meter high posts that had to be installed in a narrow, confined space, the logistics of getting the materials into place were challenging. Despite these difficulties, the Elite team meticulously planned the installation process. The narrow access via a back alley, combined with the heavy rain throughout the construction, created further delays. However, the team’s problem-solving skills and commitment to quality workmanship ensured that the project continued to progress.
Reflection and Reward
The completion of this project was especially rewarding for Scott, the builder at Elite Additions. The challenges of working with a back alleyway for access, as well as the difficulties presented by the staircase and clearstory, made this a particularly intricate build. However, seeing the final product come together and knowing that Jeremy was thrilled with the results made all the hard work worthwhile. The project transformed Jeremy's home into a spacious, functional, and visually striking 5-bedroom residence, which exceeded his expectations. Scott and the team at Elite Additions were proud to be part of a project that involved such complex design challenges and to see the finished home standing as a testament to their problem-solving and craftsmanship.
Key Takeaways:
  • Proactive Problem-Solving: Elite Additions took on the challenge of redesigning the project’s engineering when the initial plans were inadequate, ensuring the project stayed on track.
  • Collaboration with Designers: Working closely with interior designer Kate from Reset Co. helped streamline the process of choosing finishes and ensuring a cohesive design.
  • Logistical Expertise: Elite Additions’ ability to navigate tight access points and manage complex structural features like the staircase and clearstory window was critical to the project’s success.
  • Client Satisfaction: The final product was a spacious, modern home that met Jeremy’s vision, despite multiple challenges throughout the process.
  • Category Amount
    Preliminaries $39,962.58
    Excavation & Drmolition $73,920.00
    Plumbing $22,138.51
    Concrete $37,319.46
    Termite Treatment $5,198.51
    Structural Steel $110,688.51
    Carpentry Materials $224,394.41
    Brickwork $12,790.71
    Windows & Skylights $1,650.00
    Roofing $24,488.04
    Electrical $62,578.91
    Plaster $36,881.89
    Flooring $13,297.11
    Ground Floor Bath/Laundry $12,925.00
    Stairwell Ensuite $7,935.69
    Bedrooms $17,600.00
    Painting $32,148.51
    Total $797,869.47
    Conclusion
    This project highlights Elite Additions’ expertise in handling complex residential renovations, showcasing their ability to solve problems creatively and deliver high-quality results.